These works were looked at in November 2017, tendered in December 2017 and awarded in March 2018. The project was completed March 2019.

  • The dismantle/disconnection of the Eneabba Wet Concentrator plant electrical apparatus (all field motors/instruments/switch rooms).
  • The re-erection of the Eneabba Wet Concentrator plant Electrical apparatus.
  • The installation of field cabling (Communication / LV / HV / Earthing / Instrumentation).
  • The installation of field Instrumentation (Analogue / Digital / Telemetry Instruments).
  • PLC Wiring Changes.
  • HV Terminations.
  • The installation of field lighting and general power.
  • Dry and Wet commissioning